RE: IE WB2: How to test Backup Interface?

From: simon hart (simon.hart@btinternet.com)
Date: Sun Apr 10 2005 - 07:19:42 GMT-3


Ian,

This is fine in a home lab environment. During the lab however you will not
have a chance to taking down ports on the Frame switch

S.

-----Original Message-----
From: nobody@groupstudy.com [mailto:nobody@groupstudy.com]On Behalf Of Ian
Henderson
Sent: 10 April 2005 11:12
To: san
Cc: Cisco certification
Subject: Re: IE WB2: How to test Backup Interface?

On Sat, 9 Apr 2005, san wrote:

> Is there any other way to test this.?

I do this by shutting down the physical serial or E1 port on the frame
switch.

Rgds,

- I.

--
Ian Henderson CCNA, CCNP
Senior Network Engineer

iiNet Limited Chime Communications Pty Ltd



This archive was generated by hypermail 2.1.4 : Tue May 03 2005 - 07:54:55 GMT-3