Rip over isdn

From: ccie2be (ccie2be@nyc.rr.com)
Date: Tue Apr 05 2005 - 18:24:01 GMT-3


Hi guys,
 
If rip is running over an isdn link using ppp encap and the task states or
implies that that isdn link shouldn't flap, what are the config options that
should be considered?
 
Here's my list:
 
1, ip rip trigger
 
2. snapshot routing
 
Given these 2 options, what's the "best" practice? How do I decide which
option to use?
 
 
 
Also, I think other options such as dialer watch, backup int, etc aren't
good because then, in essence, the isdn link is down unless there's a
problem elsewhere in the network. Do you all agree?
 
 
Are there any options I should be considering?
 
TIA, Tim



This archive was generated by hypermail 2.1.4 : Tue May 03 2005 - 07:54:53 GMT-3