OOT: Datacentre migration question

From: Arista Wirawan <arista.wirawan_at_gmail.com>
Date: Fri, 18 Jan 2013 21:58:51 +0800

Sorry for the OOT. I was interviewed last few days ago and asked this
question. It can not get out of my head. So I need to burst it out of my
mind. Appreciate if anyone of you can help me. Thank you in advance.

Here the question:
We want to consolidate from 9 datacentres to 4 datacentre to reduce
opex/capex. What is your steps, proces, strategy? New technology that
support it?
No impact expected on the quality of network services and day to day
operation.

Sorry if you don't like it please just delete my email.
Probably my interviewer also in this milis and read this email.

Best Regards,
ARISTA

( Please excuse misspelled words, sentence structure and the brevity of
this email as it was sent via a mobile device)
On 17 Jan, 2013 10:01 PM, "Tauseef Khan" <tasneemjan_at_googlemail.com> wrote:

> To set the multicast boundary for PIM BSR do i need to block the following
> two groups on the interface:
> 224.0.1.39
> 224.0.1.40
>
> like this?
> ip access-list 1 deny 224.0.1.39
> ip access-list 1 deny 224.0.1.40
> ip access-list 1 permit any
>
> int gi0/0
> ip multicast boundary 1 out
>
> Rgards
>
>
> Blogs and organic groups at http://www.ccie.net
>
> _______________________________________________________________________
> Subscription information may be found at:
> http://www.groupstudy.com/list/CCIELab.html

Blogs and organic groups at http://www.ccie.net
Received on Fri Jan 18 2013 - 21:58:51 ART

This archive was generated by hypermail 2.2.0 : Sun Feb 03 2013 - 16:27:17 ART