T-1 WAN Configuration Using VWIC-2MFTs

From: kwindancer (kwindancer@excite.com)
Date: Thu Feb 22 2007 - 19:56:23 ART


Hello,

I am doing a T-1 migration between two sites using
Cisco 3825 routers and VWIC-MFT modules with the integrated
CSU/DSUs at both ends. We're replacing 3620 routers with the
T-1 WIC modules and external CSU/DSU's. The T-1 is provisioned already and has been working fine with the old routers.

My question has to do with clocking on the new VWIC MFT routers.

Do I set one router as source clock internal and the other router as source clock line? Right now this is how our CSU/DSUs are configured: source clock internal at one site and source clock line at the other site.

Thanks.

Kim



This archive was generated by hypermail 2.1.4 : Thu Mar 01 2007 - 07:38:47 ART