Hello,
I am doing a T-1 migration between two sites using
Cisco 3825 routers and VWIC-MFT modules with the integrated
CSU/DSUs at both ends. We're replacing 3620 routers with the
T-1 WIC modules and external CSU/DSU's. The T-1 is provisioned already and has been working fine with the old routers.
My question has to do with clocking on the new VWIC MFT routers.
Do I set one router as source clock internal and the other router as source clock line? Right now this is how our CSU/DSUs are configured: source clock internal at one site and source clock line at the other site.